1. Milestone-Meeting in Warstein

The first milestone meeting or the second overall project meeting took place in Warstein from 27. to 28.06.2017 and was organized by Infineon AG. Various line tours took place, in which the representatives of the project partners had the opportunity to visit the production of high-performance electronic components at Infineon AG. At the same time, the Fraunhofer Institute for Production Technology IPT presented smart devices, such as smart glasses, which can be used to support the assembly workers. Furthermore, a summary of the requirements survey, which took place within the framework of the first work package, as well as the application scenarios with the specific requirements were presented. Finally two workshops took place, in which on the one hand the modeling of mounting systems and and on the other hand the components of the control system and the related provision of information were discussed.